Bio Pharma Processing Equipment

Manway your way – extending PM cycle

gfx_style25
Material Used FEP/VMQ Silicone
Problem solved Technical

The Situation

A globally recognized Biopharma plant was experiencing manway gasket premature disintegration.  Risk mitigation required a frequent preventative maintenance schedule.  The required PM schedule for this seal drove the downtime schedule for the entire bioreactor line.

 

The Ask

Propose a seal which could resist reagents & aggressive cleans to extend production line uptime

 

The Solution

Darcoid proposed a FEP encapsulated o-ring custom sized to existing seal gland

 

The Success

  • Skid production line up time extended by 14 days
  • Zero instance of process contamination.
  • Ongoing predictable seal performance is assured regardless of influences inside and outside the supply chain by deploying Darcoid’s Seal Performance Creep controls
gfx grid bgstyle1m
gfx grid bgstyle1m

Related Resources

Bio Pharma Processing Equipment
The product owner for a leading manufacturer of micro fluid metering equipment was facing a significant reliability problem threatening their market leading..
Bio Pharma Processing Equipment
A global Biopharma leader needed to replace a legacy seal no longer supported by the OEM. They had no prints or specifications to guide their resolution path.
Bio Pharma Processing Equipment
A globally recognized Biopharma plant was experiencing manway gasket premature disintegration. Risk mitigation required a frequent preventative maintenance..
A globally recognized Biopharma plant was experiencing manway gasket premature disintegration. Risk mitigation required a frequent preventative maintenance schedule. The required PM schedule for this seal drove the downtime schedule for the entire bioreactor line.
FEP/VMQ Silicone
Technical