The Situation
Contract manufacturer was unable to ramp production of a subassembly due to long lead time for a globally sourced molded seal.
The Ask
Low price point, specification compliant EPR seal with high production volumes landed within 6 weeks.
The Solution
Utilizing our fast-tooling capability with trusted manufacturing partners we deployed a quality assured supply chain capable of supporting >5M parts annually, with initial 500,000 parts from new tooling landed, inspected and approved inside of 5 weeks.
The Success
- The quality assured, specification compliant product removed a critical gating item for our customer, allowing them to drive to anticipated revenue goals.
- Darcoid’s Performance Creep controls assure predictable seal performance regardless of influences inside and outside the supply chain